Deshuttering in Construction – Slab & Beam De-Centering Procedure
🔹 Introduction
Deshuttering (also called decentring or formwork removal) is a crucial activity in RCC construction. It refers to the removal of shuttering/formwork after the concrete has gained sufficient strength. Proper Deshuttering ensures structural safety, avoids cracks, and maintains the designed shape and finish.
🔹 Important IS Code Reference
According to IS
456:2000 (Clause 11.3.1) – the time for Deshuttering depends on concrete
strength, span, type of member, temperature, and curing.
🔹 General Time for Deshuttering (As per IS 456:2000)
- Vertical Formwork (Columns, Walls, Sides of
Beams): 16–24 hours
- Soffit Formwork (Slabs, Beams):
- Slabs (props left under) → 3 days
- Beams (props left under) → 7 days
- Removal of Props:
- Slabs (up to 4.5 m span) → 7 days
- Slabs (over 4.5 m span) → 14 days
- Beams & Arches (up to 6 m span) → 14 days
- Beams & Arches (over 6 m span) → 21 days
🔹 Deshuttering Procedure
- Check Concrete Strength → Ensure minimum curing time has passed.
- Start with Non-Load Bearing Shuttering → Remove side shutters of beams/columns
first.
- Remove Props Gradually → Never remove all props at once; remove
alternately to avoid shock load.
- Maintain Safety → Workers should use safety gear, and no
sudden hammering should be done.
- Curing After Deshuttering → Continue curing exposed concrete for at
least 7 days.
🔹 Quality & Safety Points
✔ Always follow IS code
guidelines.
✔ Check proper line,
level, and surface finish after shutter removal.
✔ Never deshutter early;
it may cause cracks, sagging, or even failure.
✔ Remove formwork
carefully to avoid damaging edges & corners.
🔹 Final Note
Deshuttering is not
just about removing shuttering material—it’s about ensuring that the RCC
structure has achieved enough strength to carry its own load safely. A proper
schedule, skilled supervision, and careful removal make the process successful.


Comments
Post a Comment